The
Alternatives Analysis/Draft Environmental Impact Statement (AA/DEIS) portion of the D2 Study was completed on May 17, 2010, with the closing of the 45-day Comment Period on the DEIS. This concluded a 3-year study effort that began in May 2007 with the initial Public Scoping Meeting. Over the course of the Study, the Study Team met with four Advisory Committees, the DART Board of Directors, the Dallas City Council Transportation and Environment Committee, numerous individuals and organizations, and the general public to receive input on the alternatives, evaluation process, and the analysis contained in the DEIS.
The comments, questions, and suggestions submitted during the DEIS comment period have been documented in the Public Hearing Summary Report.
Traditionally, this is the point in the project development process where the DART Board of Directors considers all the comments, reviews the AA/DEIS technical findings, and selects a Locally Preferred Alternative (LPA). Once an LPA is selected, it would advance into Preliminary Engineering (PE) to support the preparation of the Final EIS. All comments received on the Draft EIS will be documented and addressed in this Final EIS.
However, several factors resulted in a postponement in selecting the LPA for D2, including:
In early 2011, DART was awarded $700,000 in Federal Funding with which to conduct additional alternatives analysis work. When the Study begins, DART will reinitiate meetings with stakeholders, other advisory committees and the general public to review new or refined alternatives and build support for a future LPA decision.